FESCO New Electricity Connection Online

Applying for a Faisalabad Electric Supply Company (FESCO) New Connection Online is now faster, easier, and transparent thanks to the Electricity New Connection (ENC) Online Application System. You need a new meter connection for commercial or residential use? FESCO provides a streamlined digital process.

This complete guide / explanation will help you: How to apply for FESCO electricity new connection, required documents, connection charges, demand notice fees, timelines, and tracking methods.

FESCO New Connection Online | Step by Step ENC Application Guide
Step-by-step visual guide to apply for FESCO New Connection Online via ENC Portal

What is FESCO New Connection Online?

FESCO New Connection Online allows consumers of power to apply for a new hassle-free WAPDA electricity connection via a official FESCO ENC Online Portal. ENC portal supports: Domestic connections, Commercial connections, Industrial connections, and Agricultural connections

You can for a new connection: upload documents, track application status, pay demand notice, and confirm meter installation online.

How to Apply for FESCO New Connection Online

Step 1: Prepare Required Documents

Before starting the New Connection Application Online, keep scanned copies of:

  • Applicant CNIC
  • Witness CNIC (attested)
  • Property ownership documents or NOC
  • Neighbor’s recent electricity bill
  • Wiring test report (from licensed electrician)

These are mandatory required documents to apply for FESCO new connection.

Step 2: Visit FESCO ENC Portal

Go to the official ENC Portal (FESCO) and click Apply New Connection.

  • Enter neighbor’s utility bill reference number
  • System auto-detects feeder, subdivision, and area

This ensures correct load verification and meter installation planning.

Step 3: Fill ENC Online Application Form

Provide accurate details:

  • Applicant Details: Applicant’s Name, Applicant’s CNIC, mobile number, and email Address.
  • Address Details: Installation Address and postal address (e.g. 38,000)
  • Connection Type:
    • Domestic
    • Commercial
    • Industrial
    • Agricultural
  • Load Requirement Calculation (kW)
  • Ownership status (Owner/Tenant)

Note: Incorrect data may lead to application rejection.

Step 4: Upload Documents

Upload all the relevant documents in PDF / JPG format within size limits provided.

Step 5: Submit & Get ENC Tracking ID

After submission of an application, you receive an Tracking ID by ENC. This tracking id will be used for FESCO new connection tracking.

What you can do after submission:

  • Print application (for record)
  • Track verification progress (via tracking id)
  • Check FESCO demand notice status (via tracking id)
  • Upload payment receipt

FESCO Demand Notice & Meter Installation Process

Once documents and site are verified via an agent:

  1. FESCO Demand Notice is issued
  2. Pay through authorized banks
  3. Upload paid challan on portal
  4. FESCO technical team schedules meter installation

FESCO New Connection Processing Time:

CategoryLoad RangeProcessing Time
Category-1Up to 15 kWUp to 30 days
Category-216–70 kW60–90 days
Category-371–500 kW90+ days (inspection required)

FESCO New Connection Charges (Demand Notice Fees)

FESCO Single Phase Meter Demand Notice Fee:

Service Line LengthCharges
1 – 40 metersRs. 9,000
41 – 100 metersRs. 9,000 + Rs. 800/m
101 – 160 metersRs. 57,000 + Rs. 1,000/m

FESCO Three Phase Meter Demand Notice Fee:

Service Line LengthCharges
1 – 40 metersRs. 35,000
41 – 100 metersRs. 35,000 + Rs. 1,000/m
101 – 160 metersRs. 35,000 + Rs. 1,100/m
161 – 280 metersRs. 161,000 + Rs. 1,200/m

These include FESCO new connection meter fee and infrastructure cost.

FESCO Offline New Connection Process

If you prefer manual application:

  1. Visit nearest FESCO Customer Services Center / SDO Office
  2. Collect & fill new connection form
  3. Attach required documents
  4. Site inspection & load verification
  5. Receive demand notice
  6. Pay bank challan
  7. Meter installation & activation

Types of FESCO Connections Supported

  • FESCO Domestic Connection
  • FESCO Commercial Connection
  • FESCO Industrial Connection
  • FESCO Agricultural Connection

Load requirement and connection charges vary by category.

Track FESCO New Connection Status Online

For tracking new electricity connection’s status use:

  • ENC Tracking ID
  • CNIC or application reference

Track stages:

  • Verification
  • Site visit
  • Demand notice issued
  • Payment confirmed
  • Meter installed

This is called FESCO new connection tracking ID system.

Frequently Asked Questions (FAQs)

Visit the FESCO ENC Portal, submit application, upload documents, pay demand notice, and track using ENC Tracking ID.

Applicant’s CNIC, Witness CNIC, property proof or NOC, neighbor’s Wapda bill, and wiring test report.

Up to 30 days for domestic, 60–90 days for commercial, and 90+ days for industrial connections.

It is a payment slip issued after application approval covering meter and service line charges.

Starts from Rs. 9,000, depending on service line length.