FESCO New Electricity Connection Online
Applying for a Faisalabad Electric Supply Company (FESCO) New Connection Online is now faster, easier, and transparent thanks to the Electricity New Connection (ENC) Online Application System. You need a new meter connection for commercial or residential use? FESCO provides a streamlined digital process.
This complete guide / explanation will help you: How to apply for FESCO electricity new connection, required documents, connection charges, demand notice fees, timelines, and tracking methods.
What is FESCO New Connection Online?
FESCO New Connection Online allows consumers of power to apply for a new hassle-free WAPDA electricity connection via a official FESCO ENC Online Portal. ENC portal supports: Domestic connections, Commercial connections, Industrial connections, and Agricultural connections
You can for a new connection: upload documents, track application status, pay demand notice, and confirm meter installation online.
Once your FESCO new connection is active, you can check FESCO Bill Online instantly using your reference number.
How to Apply for FESCO New Connection Online
Step 1: Prepare Required Documents
Before starting the New Connection Application Online, keep scanned copies of:
- Applicant CNIC
- Witness CNIC (attested)
- Property ownership documents or NOC
- Neighbor’s recent electricity bill
- Wiring test report (from licensed electrician)
These are mandatory required documents to apply for FESCO new connection.
Step 2: Visit FESCO ENC Portal
Go to the official ENC Portal (FESCO) and click Apply New Connection.
- Enter neighbor’s utility bill reference number
- System auto-detects feeder, subdivision, and area
This ensures correct load verification and meter installation planning.
Step 3: Fill ENC Online Application Form
Provide accurate details:
- Applicant Details: Applicant’s Name, Applicant’s CNIC, mobile number, and email Address.
- Address Details: Installation Address and postal address (e.g. 38,000)
- Connection Type:
- Domestic
- Commercial
- Industrial
- Agricultural
- Load Requirement Calculation (kW)
- Ownership status (Owner/Tenant)
Note: Incorrect data may lead to application rejection.
Step 4: Upload Documents
Upload all the relevant documents in PDF / JPG format within size limits provided.
Step 5: Submit & Get ENC Tracking ID
After submission of an application, you receive an Tracking ID by ENC. This tracking id will be used for FESCO new connection tracking.
What you can do after submission:
- Print application (for record)
- Track verification progress (via tracking id)
- Check FESCO demand notice status (via tracking id)
- Upload payment receipt
FESCO Demand Notice & Meter Installation Process
Once documents and site are verified via an agent:
- FESCO Demand Notice is issued
- Pay through authorized banks
- Upload paid challan on portal
- FESCO technical team schedules meter installation
FESCO New Connection Processing Time:
| Category | Load Range | Processing Time |
|---|---|---|
| Category-1 | Up to 15 kW | Up to 30 days |
| Category-2 | 16–70 kW | 60–90 days |
| Category-3 | 71–500 kW | 90+ days (inspection required) |
FESCO New Connection Charges (Demand Notice Fees)
FESCO Single Phase Meter Demand Notice Fee:
| Service Line Length | Charges |
|---|---|
| 1 – 40 meters | Rs. 9,000 |
| 41 – 100 meters | Rs. 9,000 + Rs. 800/m |
| 101 – 160 meters | Rs. 57,000 + Rs. 1,000/m |
FESCO Three Phase Meter Demand Notice Fee:
| Service Line Length | Charges |
|---|---|
| 1 – 40 meters | Rs. 35,000 |
| 41 – 100 meters | Rs. 35,000 + Rs. 1,000/m |
| 101 – 160 meters | Rs. 35,000 + Rs. 1,100/m |
| 161 – 280 meters | Rs. 161,000 + Rs. 1,200/m |
These include FESCO new connection meter fee and infrastructure cost.
FESCO Offline New Connection Process
If you prefer manual application:
- Visit nearest FESCO Customer Services Center / SDO Office
- Collect & fill new connection form
- Attach required documents
- Site inspection & load verification
- Receive demand notice
- Pay bank challan
- Meter installation & activation
Types of FESCO Connections Supported
- FESCO Domestic Connection
- FESCO Commercial Connection
- FESCO Industrial Connection
- FESCO Agricultural Connection
Load requirement and connection charges vary by category.
Track FESCO New Connection Status Online
For tracking new electricity connection’s status use:
- ENC Tracking ID
- CNIC or application reference
Track stages:
- Verification
- Site visit
- Demand notice issued
- Payment confirmed
- Meter installed
This is called FESCO new connection tracking ID system.