LESCO New Electricity Connection

Apply LESCO New Electricity Connection Online

Procedure to Apply for LESCO’s New Connection

Check the step by step process to apply for LESCO’s new electricity Connection

Step# 1 – Open Electricity New Connection (ENC) System Link and Submit the new connection’s Application form online.

Step# 2 – Click on Apply and Fill the Form Information Required

Apply LESCO New Electricity Connection Online
  • Choose Distribution Company “LESCO”
  • Add Category Type as per the requirement of new electricity connection.
  • Add LESCO’s Sub Division as per your location.
  • Add Reference No# of LESCO’s Electricity bill *If you already having connection at the premises, provide that reference number. if you don’t have connection, add your neighbor’s reference number.
  • Choose connection type: Domestic, Commercial, Industrial, Agriculture, Tube well, Temporary, General Services, Residential Colonies, and Street Light.
  • Enter NTN – National Tax Number (If Available).
  • Enter STRN – Sales Tax Registration Number (If Available).
  • Select Application Status: If you own the property, select Owner, or if its a rental property, select Rental.
  • Add Applicant name.
  • Add Applicant’s Father’s name.
  • Add National Identity Card NIC/CNIC number.
  • Add Current/Present address.
  • Add Mobile phone number 1 & 2.
  • Add contact person’s name as per phone number/details provided.
  • Add relevant contact person’s mobile phone number.
  • Add contact person’s present address.
  • Add relationship with the Applicant.
  • Add Email (If Available).
  • Current Number of electricity meters already installed.
  • Add minimum load in (KWH).
  • Add address of the Premises.
  • Add Neighbors name and address.
  • Choose installation company of meter: Shahid & Co or Sajjad Brothers.

Step# 3 – Add Scanned copy of the required documents, “Check the below listed required documents”

  • Proof of ownership: Documents (Registry, Farred, Allotment Letter, or Baynama) All provided documents should be attested by Notary Public or Class-one officer.
  • Written Undertaking on Stamp-paper – should be confirmed by the Oath Commissioner.
  • If property have multiple owner – use power of attorney on stamp paper.
  • If Applicant is a renter than obtain – Get no objection certificate from the owner of the property.
  • Attested CNIC (Copy) of Applicant
  • Attest CNIC (Copy) of 2 Witnesses. (If meter is single phase no witness required)
  • Copy of Neighbor’s electricity bill.

Step# 4 – After Submitting all the required information, Submit application along with the copy of all the above required documents

Step# 5 – Print submitted application form online

Step# 6 – Along with printed submitted application form, attach hard-copy of all the above listed documents

Step# 7 – Submit all the above documents to the relevant office i.e. the LESCO office.

Step# 8 – After getting verification LESCO will issue demand notice.

Step# 9 – Pay required fee to the bank along as mentioned in the demand notice.

Step# 10 – Submit paying fee submit the slip/demand notice to relevant office i.e. the LESCO office.

Last Step# – After completing the verification process LESCO will start installation of the New Electricity Connection

Frequently Asked Questions FAQs

  1. Fill the online application form.
  2. Attach scanned copy of all the relevant documents.
  3. Send printed application and relevant documents to LESCO office.
  4. Get demand notice after verification and pay fee to bank.
  5. Submit the fee slip to relevant LESCO office. All Done!

Connection fees may vary as per the requirement of meter:

  • Three Phase LESCO’s New Meter Fee is 63,450 PKR Will effective from 1st July 2024
  • Single Phase LESCO’s New Meter Fee Starts from 7,240 PKR confirmed by LESCO’s official site. Its recommended to confirm fee from nearest LESCO office

You need to visit nearest LESCO office to get the status of new connection’s application or Track new connection’s status online @ https://enc.com.pk/

It depends on the situation, normally it takes 30 to 75 days.

Simply fill new wapda’s meter application and submit required documents to LESCO office and pay required fee as per demand notice. All Done!